← belizelaw.ai · Belmopan (Zoning And Control Over Building Construction) By Laws, Cap. 86s06 · PART III — Control Over Building Construction

Temporary structures

Belmopan (Zoning And Control Over Building Construction) By Laws, r. 15 · Revised Edition 2020

(1) The erection of any temporary structure for a period exceeding seven days shall only be allowed in certain circumstances, and for a limited period. When a temporary consent is issued, it shall be on the basis that the structure is removed on a date prior, but not exceeding, the expiry date of the consent. 30 Belmopan City Council (2) Following the completion of any permanent structure, any temporary structure on the same site must be removed within twenty-eight days of the completion date. (3) Temporary boardings to ensure greater safety of buildings during works of development shall be only allowed during the period of construction. operation of By- laws.
Have a question about this section? Ask belizelaw.ai →