Where, for the purpose of executing any work, a licensee breaks open any street or bridge, or any drain or sewer or tunnel, he shall with all convenient speed and to the reasonable satisfaction of the persons having the control or management thereof complete the work and fill in and consolidate the ground and reinstate and make good the street or the sewer, drain or tunnel, as the case may be, and remove all rubbish resulting from their operations and shall, after replacing and making good the street, keep it in good repair for three months and for such further time, if any, not being more than twelve months in the whole, as the soil may continue to subside.