← belizelaw.ai · Electricity (Tariffs, Fees And Charges) Bye-Laws, Cap. 221s06 · PART III — FULL TARIFF REVIEW PROCEEDINGS
Notice of FTRP
Electricity (Tariffs, Fees And Charges) Bye-Laws, r. 16 · Revised Edition 2020
(1) At least 160 days prior to the commencement of a FTP,
a licensee, in coordination with the Commission, shall provide public notice, in accordance with bye-law 6 above, of the commencement of a FTRP.
(2) Such notice shall describe the following–
(a) the purpose and nature of a FTRP;
34 Electricity
(b) a summary of the issues to be addressed;
(c) the process for the FTRP and the opportunities available for and participation;
(d) indication of the time, date and place for the
(e) the fact that members of the public can obtain up-to-date information on the schedule of the proceeding at the office of the Commission and at the licensee’s principal business office.